   Overview
   What You Need
   Installing OpenTTD
 
 Rail Building
   Fundamentals
   Stations
   3-Way Junctions
   4-Way Junctions
   Depots
   Check Points
 
 Rail Junctions
   Basic Junctions
   Double-cross Junctions
   T-Junctions
   Crossover Junctions
   Station Configuration
   Complex Junctions
   Realistic Track Configs
 
 Other Tips
   Towns
   Feeders
   Vehicle Usage
 
 Miscellaneous
   Vehicle List
 
 Downloads
   Saved Games
   Scenarios
   Music
   Saved Game Manager
   TTDAlter
   TTDX Editor
 
 Other Resources
   Links
   The TT Forums
   The Repository
   TT Semi-FAQ
   Locomotion Depot
   owenrudge.net




Rail Building
  Part 4: Four-Way Junctions

Three-way junctions are good when you have a branch line breaking off the main line. But what if you've got another branch line nearby? It can often be more efficient to build a four-way junction for all of these. This page provides some example four-way junctions and details on when to use them. You may also wish to reference the Rail Junctions section of this site for more inspiration.

Basic JunctionBasic Four-Way Junction

This type of junction is pretty awful, really. Try not to use them if possible.

Pros:

  • Cheap and easy to build
  • Trains don't have to slow down to climb a slope

Cons:

  • Can only handle one train at a time
  • Can quickly cause traffic jams

RoundaboutRoundabout

This junction is arguably an improvement on the basic 4-way junction, but can easily get clogged up and cause problems.

Pros:

  • Cheap and easy to build
  • Can handle up to two trains at once
  • Trains don't have to slow down to climb a slope

Cons:

  • Limited capacity
  • Can quickly cause traffic jams

Cloverleaf

The cloverleaf is the bigger brother of the half-cloverleaf. It can handle substantial amounts of traffic well, although it's important to note that the size of the cloverleaf in this picture has been reduced. It's best you make it so your longest train can fit completely into one of the turning tracks without blocking the main line behind it. See some of the junctions on the Double Track Cross Junctions page for more examples. Note also that tunnels are used instead of bridges, as trains have to slow down to the maximum speed of the bridge, whereas tunnels have no speed limit. This is a good junction in the respect that it has a high capacity, but it's not so useful for hilly or cluttered areas due to the large amount of space required.

Pros:

  • Can handle a large number of trains at a time
  • Traffic jams are unlikely

Cons:

  • Trains must slow down to climb a slope (can be 'fixed' with TTDPatch)
  • Trains must turn left to turn right. This could lead to trains getting lost. (Can be fixed by using checkpoints with TTDPatch)
  • Trains turning right must loop around.
  • Costs more to build
  • Takes up a large amount of space
Spaghetti

Pros:

  • Handles a large number of trains at once
  • Traffic jams are unlikely
  • Trains don't have to loop around as they do in a cloverleaf.

Cons:

  • Trains must slow down to climb a slope (can be fixed with TTDPatch)
  • Trains must turn left to turn right. This could lead to trains getting lost. (Can be fixed by using checkpoints with TTDPatch)
  • Takes up a large amount of space
  • Costly to build
  • Indirect path
Complex Roundabout (CRAB)

Unlike the spaghetti or cloverleaf junctions above, the tracks on the CRAB split before they merge so a trains are less likely to encounter a red signal. Also, it does not give preference towards any track so it is great for where there are many trains coming from and going to all directions.

With a simple roundabout, there is only one looping track while with the complex version there are three. They each start in the centre and work their way outwards. Trains heading North East (where North is the top of the picture) from South East will go to the inside track. This then joins with the South West to North West track and becomes the middle track. Then finally it becomes the outside line after joining the North West to North East line and leaves the junction.

You can also use the CRAB on two-track lines, that is, a line with two tracks going up and two tracks going down. To see an example of this, click here. Although it appears complex, it is one of the most efficient anywhere-to-anywhere 4-way 4-track junctions you're likely to find. If you know of a better one, don't hesitate to tell me and the world about it.

Pros:

  • Handles a large number of trains at once
  • Traffic jams are unlikely
  • Trains don't have to loop around as they do in a cloverleaf.
  • Tracks split before they merge, avoiding traffic problems.

Cons:

  • Trains must slow down to climb a slope (can be fixed with TTDPatch)
  • Takes up a large amount of space
  • Costly to build
  • Indirect path

Don't forget to check out the Rail Junctions section for many more examples of junctions!

 